News and Insights
-

Heating Restoration Begins December 15
This is to inform you that starting Monday, December 15, Archway will begin the process of restoring heat in the units.
- At this stage, we are targeting 101 units.
- 80 units where all project work has been fully completed, will have heating restored at normal capacity.
- 21 units that still contain the old heating elements will have heating restored at limited capacity. This is because the new system is designed to operate with a significantly lower water temperature, which is not compatible with the older elements.
- Work will continue in the remaining units not listed above as we address the outstanding issues.
Thank you for your patience, cooperation, and understanding.


Leave a comment